2023 the year for Guy Road pathway
WORKS for the Guy Road Shared Pathway project are expected to re-commence this month. Here’s where the project is at, according to Bass Coast Shire: Concrete footpath * The concrete footpath from Jamieson Street to Balcombe Street has been...
WORKS for the Guy Road Shared Pathway project are expected to re-commence this month.
Here’s where the project is at, according to Bass Coast Shire:
Concrete footpath
* The concrete footpath from Jamieson Street to Balcombe Street has been completed with the exception of areas where Telstra Pits require adjustment. Telstra will arrive on January 23, to make the necessary adjustments prior to the completion of the concrete.
* Tenby Point - Concrete footpath works will be undertaken from January 11 to 27, 2023.
Boardwalk
* Current works are being undertaken at the intersection of Guy Road and Argent Road. This is the final section of the boardwalk.
Gravel pathway
* The pathway between Jamieson Street and Brick Kiln Road is almost complete.
The Guy Road Shared Pathway, expected to be completed in March, will be a six-kilometre-long, 2.5-metre-wide shared cycling and walking link between the Corinella Community Centre to the Bass Valley Primary School and Children’s Centre, via Tenby Point. The pathway will link into existing pathways connecting to the Bass Highway in one direction and Coronet Bay in the other.