Drainage renewal for Pioneer Bay

BASS Coast Shire Council has announced the appointment of Wiltrack Earthmoving Pty Ltd as part of their annual supply contract for the drainage renewal works behind 45 Sonia Crescent. The project is expected to commence week ending March 3, 2023...

Sentinel-Times  profile image
by Sentinel-Times

BASS Coast Shire Council has announced the appointment of Wiltrack Earthmoving Pty Ltd as part of their annual supply contract for the drainage renewal works behind 45 Sonia Crescent.

The project is expected to commence week ending March 3, 2023, and be completed by late March 2023, subject to favourable weather conditions. 

The total cost of the project is estimated to be approximately $85,000 and is part of the Council’s 2022/23 Capital Works Program.

The drainage renewal works are an essential part of the Stormwater Drainage Renewal Program under the 2015 Drainage Services Asset Management Plan. 

The project will ensure delivery of the adopted Community Service levels and help manage stormwater runoff and flows of the catchment within the designated drainage reserve area.

As part of the project, Wiltrack Earthmoving Pty Ltd will remove redundant and damaged drainage pipes and structures behind property 45 Sonia Crescent. 

They will also construct a junction pit, install underground stormwater pipes and a drainage outlet structure with rock bags, carry out erosion protection and re-establishment works using rock bags and connect existing house drainage connections to the new junction pit.

The community, residents, businesses, and other stakeholders will be kept up to date with the project via website updates, letter box drops or mail outs where appropriate. 

For information or assistance during this project, please contact:

• Wiltrack Earthmoving Pty Ltd – Project Supervisor – Michael Wilson 0409 560 886

• Bass Coast Shire Council’s Infrastructure Delivery Team, John Armstrong - Project Officer on 1300 BCOAST (226 278) or (03) 5671 2211 (business hours Monday – Friday)

• Visit https://engage.basscoast.vic.gov.au/pbstorm to get the latest updates on this project.